Item |
Capacity |
Comments |
Diesel Generator |
200 kVA (160 kW) |
24hr runtime backup fuel |
D M Water plant |
6 kl / hr |
Additional storage in place |
Boiler |
400 kg / hr |
Pressure safety valve set kg / cm2g : 10.54 |
Cooling tower |
125 TR |
Connected to all SS mixing vessels |
Air compressor |
70 CFM |
Maximum working pressure 7 kg / cm2 |
Scrubber |
3,000 CFM |
PP/FRP Column with Inbuilt recirculation Tank |
HVAC |
6k, 5k, 5k, 3.2k CFM |
Mfg areas 1&2, Chemical & Micro lab, Filling area |
Goods lift |
2,500 kg x 2 |
RM store, PM Store |
MHE |
2 Bo Stackers, HoPT |
1.5 Ton each, 2 Ton each (respectively) |
Fire hydrant system |
2 hr inhouse water storage |
GIDC Fire station at 500m from the unit |
ETP |
30 kL / day |
GIDC cETP connection and membership in place |
Distribution transformer |
400 kVA |
Installed |